ERIC OCAMPO

I am a Microsoft Access Certified Specialist with an Electronic Sciences Degree and 20 years of solid experience in Oil and Gas projects in North America, Latin America, and the Middle East.

I’ve been working in Mechanical Completions as System Completions Database Administrator (SCDBA) using GoCompletions®, MCPlus®, Smart Completions Hexagon® and WinPCs®, and as a Database Developer, I have developed applications for Project Turnover, Completions, Materials, Preservation, Dossier reviews, Weld Tracking, Instrument loops, etc.

Contact me in LinkedIn:

© ERIC OCAMPO 2022 | All rights reserved.
ERICOCAMPO.COM

I’m Eric Ocampo

SPECIALTIES

System completions
and turnover

Completions and Turnover are closely interrelated process during the project execution.

System Completions refers to the process of ensuring that all components of a project have been properly designed, developed, tested, and integrated to meet the project requirements and specifications. In EPC projects this includes all hardware, software, and other supporting systems necessary for the project’s success.

System Turnover refers to the process of transferring custody and/or ownership of a system or subsystem (or a defined scope) from the EPC contractor to the project owner across the different defined phases. The turnover process normally follows a structured and systematic approach to ensure that all the necessary activities are completed and that the system or subsystem is thoroughly tested before it is handed over to the project owner.

While Completions is focused on the completeness granularity, Turnover is focused on the transfer of custody.
 

Related post-articles I’ve published:

System completions<br />
and turnover

is your project completions “spreadsheet-tracking” a scrambled process?

A “master system register” as a powerful tool in epcc projects

Effective management of “subsystem final walkdowns” in epc projects

Effective 1.1: turnover package dossier administration system

Punchlist Management

Punchlist Management

Punchlist management refers to the process of identifying deficiencies and managing its corrective actions.

The deficiencies may include incomplete or defective work, safety hazards, missing or damaged equipment, or other issues that depending on the category need to be addressed before the respective handover gate.

Although every project is different, at least initially, the punchlist management involves creating a comprehensive list of outstanding items during an agreed walkdown (Preconstruction, Subsystem, Final, PSSR, etc.) and a categorization process which is in correlation with the nature of the deficiency and the phase :

A) Highly Critical

B) Critical punch items that do not affect the safety nor the integrity

C) Noncritical punch items, typically beyond the scope of the contract or project.

An effective Punchlist administration

In respect of “Punchlist Data Administration,” the process involves collecting, organizing, documenting, and tracking the deficiencies to ensure that they are closed promptly and efficiently. It is typical for projects to use software tools like completions database systems to streamline the process and improve collaboration between parties.

However, for me, as SCDB, an efficient punchlist management is not only a one-dimension data tracking process but is also about optimizing the punchlist cycle: “Identify- Register-Assign-Fix-Approve.”
During this cycle, team efforts and actions are more assertive using the most effective punchlist information from the software or completions database system used by the project.

Most projects find themselves in situations that require changes during the execution; these changes very likely drive the need for data customization to help visualize, track, make decisions, and/or take actions for the project’s success.

Some examples of the requirements that I have found in my career are:

  • The creation of punchlist subcategories A1, A2, etc., for specific scopes and/or exception purposes.
  • The development of dynamic punchlist dashboards interactively grouped by milestone, fishbone, or contractor to be used in daily war room meetings to quickly review, discuss, schedule, assign, and distribute-the actions on the fly.
  • The ability to quickly visualize, review and schedule the “on-hold-due-to-materials” punchlists with Materials Management Team. This implementation allowed transparency between material orders, punchlists, and completions systems.
  • Connecting with the Planning Team to allot and measure manhours to the punchlist clearing process using “jobcards” or “workplans.” This pairing allowed more transparency of the remaining hours in the schedule.

Depending on the software the project uses, some of these requirements need more or less the manipulation of exported datasets.

Spreadsheets will likely fulfill easy data manipulation requirements. Still, more complex ones will significantly benefit from using relational database techniques and coding. However, it is an effort that might represent a challenge and an improvement opportunity for the project.

As a Completions and Turnover Database Lead, I always encourage my team in using a more effective and structured data management approach beyond the spreadsheets and Completions Database software. 

Related post-articles I’ve published:

Project deficiencies and punchlist management

2 ways of how projects could benefit more from their punchlist data

5 useful summary reports and 2 charts in EPC projects (completions & turnover)

Effective management of “subsystem final walkdowns” in epc projects.

Mechanical completions

Mechanical completions refer to the final stage of construction and pre-commissioning of a facility or plant, in which all mechanical systems and equipment have been installed, tested, and verified for the commencement of Commissioning and Start-Up activities.

During the mechanical completion process, various activities are performed, including mechanical testing of equipment, piping systems, electrical systems, and instrumentation. The testing process involves verification that equipment and systems are installed correctly, operate as intended, and meet all performance criteria. Any punchlist identified during this phase and categorized as “A” (and “B” if defined by project procedure) have to be corrected.

Turnover interdisciplinary certificates like Discipline Acceptance Certificate (DAC), or Construction Completions Certificates (CCC or SCN) to achieve the Mechanical Completion Certificate (MCCC) either by partial or complete subsystem.
 

Related post-articles I’ve published:

Mechanical Completions

5 useful summary reports and 2 charts in EPC projects (completions & turnover)

Effective management of “subsystem final walkdowns” in epc projects.

Is your project completions “spreadsheet-tracking” a scrambled process?

A “master system register” as a powerful tool in EPCC projects

Management of Checksheets, ITRs or QVDs
(Construction “A” & Pre-Comissioning “B”)

Checksheets and ITRs

The terms of Checksheets, ITRs, and QVDs have been used interchangeably depending on the project or company, nonetheless they are an essential tool for ensuring that all necessary inspections and tests are performed and that no important details are missed.

I’ve found some differences that don’t deviate them from their main purpose.

Checksheet is a document that outlines the list specific items that need to be checked during an inspection or test. The list is to be completed with checkmarks in checkboxes “YES”, “No”, “N/A” and “Punchlist” with space for initials.

Inspection and Test Report (ITR) goes a bit further than just checkmarks; it has fields to record values and more spaces to provide other details like readings, sketches and diagrams like for motor alignment.

Quality Verification Document (QVD) is a heavily Quality Assurance document that can either be a checklist of inspections for a component or a record sheet to document the results of a functional test.

Instructions and activities required to perform the inspections are described in the Inspection & Test Plan (ITP) developed by the project QAQC team.

Some examples of the inspections:

  • A ITRs.- Construction and Installation
  • B ITRs .- Precomissioning
  • C ITRs.- Commissioning

 

Related post-articles I’ve published:

5 useful summary reports and 2 charts in EPC projects (completions & turnover)

Master tag – Drawings – System scoping?

The “tag source register” in EPCC projects

Tagging, systemization, scoping, mapping, and tag validation

Tagging is the process of assigning unique identification codes (tags) to each piece of equipment, instrument, cable, and control device of the project. These tags are sourced by Engineering in lists from SPEL, SPI, Cable Schedule, Mechanical Equipment List, Line Designation Tables, etc. These lists are in a continuous revision and update process.

Systemization and Scoping

System scoping involves defining and identifying the scope of work for a specific system or subsystem within a larger project. This typically involves breaking down the overall project scope into smaller, more manageable pieces that can be more easily defined, planned, and executed.

A common practice for this activity is highlighting (or colouring) either manually or electronically drawings. Process and Instrumentation Drawing (PIDs) for process equipment like instrument, pipelines, Mechanical, Single Line Drawings (SLD) for Electrical equipment like switchgear, MCC, etc.

Tag Validation

The continuous revision and update of the Engineering lists means a need of a constant validation as it is very likely that there will be some new tags, other might have been deleted or renamed either in the tag itself or in the description.

This proper tag validation is essential to ensure the project is being executed with the most updated data from Engineering.
 

Related post-articles I’ve published:

Tagging, systemization, scoping, mapping, and tag validation

The “tag source register” in EPCC projects

A “master system register” as a powerful tool in EPCC projects

Master tag – Drawings – System scoping?

Effective 1.1: turnover package dossier administration system

Project QAQC controls management (RFI, CAR, NCR)

Project QAQC controls management (RFI, CAR, NCR)

RFI or SQ

Site queries, also known as Site Query (SQ) or Requests for Information (RFIs), are formal communication tools used in Engineering, Procurement, and Construction (EPC) projects to address questions, clarify uncertainties project specifications, or resolve discrepancies that arise during the construction phase of a project.

NCR

NCRs, on the other hand, are formal reports that document instances of non-conformance, or deviations from project requirements, specifications, or industry standards. NCRs are typically issued by quality control personnel or inspectors and are used to identify and document issues with the work being performed.

CAR

A Corrective Action Request (CAR) is a document used in project management to request corrective action to be taken when an issue or problem is identified.

In the context of EPC (Engineering, Procurement, and Construction) projects, CARs may be used to address issues related to the design, procurement, or construction phases of the project.

Although not always, NCR and CAR are in close relationship.
 

Related post-articles I’ve published:

5 useful summary reports and 2 charts in epc projects (completions & turnover)

Effective management of “subsystem final walkdowns” in EPC projects.

Precomissioning

Pre-commissioning is a critical phase during the project execution. It occurs after construction and installation but before the final commissioning stage. The goal is to ensure that the system is Mechanically completed and ready for commissioning.

During pre-commissioning, various checks, tests, and activities are performed to ensure that all components are functioning properly and meet safety and operational requirements.

Unless the project has a Pre-commissioning team, these activities are generally completed by construction prior to Mechanical Completion.
 

Related post-articles I’ve published:

Precomissioning

A “master system register” as a powerful tool in EPCC projects

Effective management of “instrument loop folders” using ms access

Is your project completions “spreadsheet-tracking” a scrambled process?

“Cause and effect” testsheet management application

Instrument Loop pack management

Instrument Loop pack management
Instrument Loop checking is a pre-Commissioning activity initiated after installation of the field instruments. (Field devices I/O via wire ways, junction boxes, and marshaling cabinets to DCS including electrical controls, interface, and final control elements).

So, before proceeding with the Loop Testing, it is essential to have identified the location, scope, specifications, and readiness of the loop. A common practice in projects is to consolidate the applicable documentation in “Instrument Loop Folders.”
 

Related post-articles I’ve published:

Effective management of “instrument loop folders” using MS Access

“Cause and effect” testsheet management application

Get efficient, not just busy. Pipeline testing: A Test package dossier management application.

The “tag source register” in EPCC projects

Management of Change (MOC), Site Instructions (SI), Field Construction Notice (FCN)

Management of Change (MOC)

MOC, or Management of Change, is a systematic process for managing and controlling changes to engineering, procurement, and construction (EPC) projects. Changes can occur at any stage of a project and can impact scope, schedule, cost, quality, or safety. Effective management of change is essential to minimize risks, maintain project objectives, and ensure the successful completion of the project.

Site Instructions (SI), Field Construction Notice (FCN)

Site instructions, also known as Field Instructions or Construction Change Directives, are formal written directives issued by the project owner, engineer, or project management team to the construction contractors or subcontractors during the execution of an Engineering, Procurement, and Construction (EPC) project. Site instructions provide clarification, additional information, or changes to the original scope, design, or construction method to ensure that the project is executed according to the project specifications, contract requirements, and industry standards.
 

Related post-articles I’ve published:

Management of Change (MOC), Site Instructions (SI), Field Construction Notice (FCN)

5 useful summary reports and 2 charts in EPC projects (completions & turnover)

Project deficiencies and punchlist management

Pipe Test Pack management

Pipe Test Pack management
Pipeline testing is a critical step in ensuring the integrity and reliability of the pipeline system, as well as ensuring that it meets the design specifications and regulatory requirements.

Pipeline testing typically involves a series of tests that are performed to check for leaks, pressure integrity, and overall system functionality. These tests may include hydrostatic testing, pneumatic testing, leak detection testing, service tests and other specialized tests, depending on the specific requirements of the project.

Usually, is the Construction Contractor who group this testing into “TestPacks” with the approval of Engineering and QAQC of the project. These testpack include the pipelines (or portions) and their pressure gauges, temperature sensors, and other testing instruments.
 

Related post-articles I’ve published:

Get efficient, not just busy. Pipeline testing: A Test package dossier management application.

Effective 1.1: Turnover package dossier administration system

Effective management of “Instrument Loop Folders” using MS Access

2 Ways of how projects could benefit more from their punchlist data

Project walkdown management

Walkdowns are physical and visual inspections that are normally conducted in construction projects to help identify and plan corrective actions to any outstanding issues or deficiencies. They are critical events for ensuring a smooth transition across the different turnover phases of the project before it is finally handed over to the owner or operator for commissioning, startup and/or operations.

Although every project is different, these are some of the most common types of walkdowns:

Contractor (or Construction) Completions Walkdown

For this type of walkdowns, the Contractor is required to initiate a completions walkdown for verification of system completeness at that time (or prior to). The Contractor shall prepare a walkdown package and must present it to the Company at the time of making their completions walkdown notice. Depending of the completeness criteria (i.e. percentage of construction ITRs or manhours) the walkdown invitation is accepted to proceed by the company.

“A” punchlists must be completed before the subsystem completions certificate (SCN) or before the Contractor submit their invoice whichever is the earliest.

Final Completions walkdowns

Final walkdowns are comprehensive and multidisciplinary walkdowns conducted between Construction/Precomissioning and Comissioning teams, sometimes they might include third-party inspection agencies.

The purpose of the final walkdown is to identify any remaining deficiencies, discrepancies, risks or non-conformances that need to be addressed before the project can be formally turned over to Commissioning.

This walkdown serves as a final assessment of a system or sub-system is made based on the status of any new punch list and/or those raised during the prior construction completions walkdowns.

Any “A” and “B” punchlists at this stage should be cleared before the transfer of custody certificate is signed unless exemptions and recategorizations agreed.

PSSR Walkdowns

PSSR walkdowns are conducted to ensure that equipment and systems are ready to be started up safely and that all necessary safety measures are in place before startup. This walkdown is typically conducted after the completion of construction, installation, and pre-commissioning activities but before the actual startup or commissioning of the facility.

During the PSSR walkdown, several parties from Engineering, Safety, Process, Commissioning, Operations and Start-up teams will inspect equipment, systems, and review procedures to ensure that any hazards associated with the startup process have been identified and properly controlled.
 

Related post-articles I’ve published:

Project walkdown management

Effective management of “Subsystem Final Walkdowns” in EPC projects.

Effective 1.1: Turnover package dossier administration system

A “Master System Register” as a powerful tool in EPCC projects

Preservation & Maintenance data implementation and management

Preservation & Maintenance data implementation and management
Preservation and maintenance management are essential aspects of ensuring the reliability, safety, and longevity of equipment and systems in industrial facilities. Proper preservation and maintenance help minimize the risk of unexpected equipment failures, costly downtime, and accidents. These practices are particularly important during periods of equipment inactivity, such as under storage, or temporary shutdowns, to prevent damage and ensure that the equipment is ready for operation when needed. Not only that, vendors and manufacturers specify the preservation activities to be followed to keep valid the equipment warranty.

Once the equipment is put under service, preservation turns into a maintenance process.
 

Related post-articles I’ve published:

“20,000 Pieces of tagged equipment”: Materials Management DB MS Access application

Project deficiencies and Punchlist Management

Materials Data Tracking Management

Once the materials and equipment have been procured, a material management process follows up, this process is essential to ensure that the required materials are delivered to the project site on time and within budget.

In addition to factors such as material availability, lead times, supplier capacity, and transportation logistics, a good strategy should consider an effective and practical communication system to easily order, track, quantify and follow up the materials.

Materials Management team usually interacts with several parties involved in this Materials supply process: Construction, Manufacturers, Warehouse, Logistics, Contractors, etc.

A proper material management execution ensures the materials are being moved safely and efficiently; any delay or setback will very likely impact budget, schedule, or safety record at the worst.
 

Related post-articles I’ve published:

Materials Data Tracking Management

“20,000 Pieces of tagged equipment”: Materials Management DB MS Access application

Project deficiencies and Punchlist Management

Get efficient, not just busy. Pipeline testing: A Test package dossier management application.

Red Line Data Management

Red Line Data Management
Red lines are typically used to indicate changes or revisions to the original engineering design documents, including drawings, specifications, and other technical documents.

The Red Line Management involves establishing clear procedures for capturing and tracking these changes and ensuring that they are properly documented, reviewed, and approved before being incorporated into the final design.
 

Related post-articles I’ve published:

Master tag – Drawings – System scoping?

A “Master System Register” as a powerful tool in EPCC projects

System Turnover Package Administration (Dossiers)

Also known as System Turnover Dossiers, Turnover Binders, Handover Dossiers, etc. These are set of documents and deliverables that provides a detailed record of the completed system, including design documents, test results, inspection reports, and other relevant information.

STPs serve as the support of the completed scope to be transferred from the construction phase to the commissioning and startup phase of the project. Upon the extent of the table of contents, a properly bookmarked and metadata electronic version of the STP could be a powerful source to track the project history of any specific scope, piece of equipment or pipeline.
 

Related post-articles I’ve published:

System Turnover Package Administration (Dossiers)

Effective 1.1: Turnover package dossier administration system

Get efficient, not just busy. Pipeline testing: A Test package dossier management application.

Is your project completions “spreadsheet-tracking” a scrambled process?

A “Master System Register” as a powerful tool in EPCC projects

Cause and Effect Matrix management

Cause and Effect Matrix management
The goal is to execute the “Cause and Effect” functional check when the initiator and actuator have completed their precomissioning checksheets.

To achieve this goal, the idea is to group C&E Function test packs with the initiator/actuator test documentation completed to prepare a baseline plan.

The typical approach

The typical approach in most of the projects, is the matrix representation in spreadsheets, where the list of initiators are listed on the frozen columns to the left and the actuators are columns to the right (with some few frozen rows at the top for the tag, description and B checksheet).

The crossings cells of the rows(initiator) vs columns (actuator) are filled with the effect (Cl – Close Valve, OP – Open valve, SD – Shutdown device), etc
 

Related post-articles I’ve published:

“Cause and Effect” Testsheet Management Application

Effective management of “Instrument Loop Folders” using MS Access

Is your project completions “spreadsheet-tracking” a scrambled process?

Copy link
Powered by Social Snap